London Central Build Blog – Week 40

This week has seen the completion of all major external works, with exception of course given to the generators, some minor armoured barrier installations and general cleaning / painting.

Fencing assembly coming together
Fencing assembly coming together
Gates being assembled
Gates being assembled
A corner of the fencing assembly reaching completion
A corner of the fencing assembly reaching completion
Pedestrian gate installed down roadside of the facility
Pedestrian gate installed down roadside of the facility
Main run of fencing reaching completion
Main run of fencing reaching completion
Main run of fencing complete, excluding razor wire and skip access panel
Main run of fencing complete, excluding razor wire and skip access panel
Spiral fire exit staircase installation underway
Spiral fire exit staircase installation under way
First section of staircase installed
First section of staircase installed
Staircase nearing landing level at first floor data hall fire exit
Staircase nearing landing level at first floor data hall fire exit
Landing platform and hand rail assembly installed
Landing platform and hand rail assembly installed
A look at the staircase as final fixings are made
A look at the staircase as final fixings are made
View from the first floor data hall fire exit onto the new staircase
View from the first floor data hall fire exit onto the new staircase
The completed fire exit staircase
The completed fire exit staircase
The completed fire exit staircase
The completed fire exit staircase
A view of the staircase and other exit routes, along with office-side plant hardware at rear of facility, ahead of fencing in
A view of the staircase and other exit routes, along with office-side plant gear at rear of facility, ahead of fencing in
An additional APC delivery with new cabinets for deployment in first floor data hall
An additional APC delivery with new cabinets for deployment in first floor data hall
Cooling stack frame reaching completion ahead of final ductwork assembly
Cooling stack frame reaching completion ahead of final ductwork assembly

London Central Build Blog – Week 39

Much like last week, as we reach the closing stages of the project progress is solid in a number of key areas. The cooling system has again taken great strides towards completion, and many rack enclosures are now in the data hall ready for building out the first pods.

Extraction duct work sleeving installed into walls
Extraction duct work sleeving installed into walls
Fans being installed into extraction duct work
Fans being installed into extraction duct work
Extraction fan installed into duct work
Extraction fan installed into duct work
A look at the highly efficient extraction fans which form part of our intelligent cooling system
A look at the highly efficient extraction fans which form part of our intelligent cooling system
A look at one of the custom 3-way duct and actuated louvred panel systems which control the remixing of air inside of the cooling system
A look at one of the custom 3-way duct and actuated louvred panel systems which control the remixing of air inside of the cooling system
Second wetbox cooler fitted atop the first cooling stack
Second wetbox cooler fitted atop the first cooling stack minus filter panels
Delivery of our palisade fencing system ready for enclosing the generator plant area
Delivery of our palisade fencing system ready for enclosing the generator plant area
Delivery of our palisade fencing system ready for enclosing the generator plant area
Delivery of our palisade fencing system ready for enclosing the generator plant area
The various gates which form part of our rear compound enclosure
The various gates which form part of our rear compound enclosure
Corner post section being constructed
Corner post section being constructed
Gate posts ahead of hanging the first set of main gates
Gate posts ahead of hanging the first set of main gates
First gate hung in place
First gate hung in place
Second gate hung, completing the first gate assembly ahead of installing palisades
Second gate hung, completing the first gate assembly ahead of installing palisades
A view down the main run of compound enclosure posts
A view down the main run of compound enclosure posts
Delivery of our specialist APC AR3200 lockable half rack enclosures
Delivery of our specialist APC AR3200 lockable half rack enclosures

London Central Build Blog – Week 38

There have again been major advancements across multiple areas of the build project this week, primarily centring around completion of the data hall infrastructure ahead of final electrical and network installations.

First inlet fan installing into cold corridor enclosure ahead of duct work installation
First inlet fan installing into cold corridor enclosure ahead of duct work installation
A view of the fan from the data hall side of the enclosure, where pre-filtered cold air will fill the air plenum and drop through the ceiling filters into the technical space
A view of the fan from the data hall side of the enclosure, where pre-filtered cold air will fill the air plenum and drop through the ceiling filters into the technical space
Our core network infrastructure UPS systems have finished being built, with a unit for both the A and B side
Our core network infrastructure UPS systems have finished being built, with a unit for both the A and B sides
Final panelling (removable for access) fitted around new fire escape opening ahead of decoration
Final panelling (removable for access) fitted around new fire escape opening ahead of decoration
Test positioning of our custom grilles ahead of extraction ducting and fans
Test positioning of our custom grilles ahead of extraction ducting and fan installations
Ductwork pieces arriving from manufacturer
Ductwork pieces arriving from manufacturer
Duct sleeve inserted into extraction opening
Duct sleeve inserted into extraction opening ahead of fan installation
Flooring for third pod completed
Flooring for third pod completed
Second cooler base test fitted to first cooling stack
Second cooler base test fitted to first cooling stack
Test positioning of further cabinets as the cold corridor is built out
Test positioning of further cabinets as the cold corridor is built out

The cooling system has come along dramatically this week, with the coolers and fans installed into their final positions, ready for the ductwork and control systems which will bring the entire setup to life.

We have a multi-stage air filtration system, which keeps the air inside of the facility supremely clean at all times. Air is drawn through first stage particle filters in the louvred panels, second stage bag filters which enclose the wet box units, third stage high density wet box filters, and fourth stage cloth filters in the ceiling grid.

London Central Build Blog – Week 37

The flooring has taken shape this week, along with completion of the first two pod containment systems. We are now ready for a final deep clean and for racks to begin making their way up to the first floor data hall.

On site construction of the cold aisle containment plenums
On site construction of the cold aisle containment plenums
Completed containment system with test rack in position
Completed containment system with test rack in position
A look across the first floor data hall as final technical flooring is installed
A look across the first floor data hall as final technical flooring is installed
The rack pods will be built out on the black areas of the floor
The rack pods will be built out on the black areas of the floor
The flooring colour scheme aids with visualising the layout of the data hall ahead of total pod population
The flooring colour scheme aids with visualising the layout of the data hall ahead of total pod population
Panorama as flooring around the first pod is completed
Panorama as flooring around the first pod is completed
Second pod flooring completed
Second pod flooring completed
Test rack positioning at end of first containment pod
Test rack positioning at end of first containment pod
Decorating continues in the ground floor facility access areas
Decorating continues in the ground floor facility access areas
Decorating continues in the ground floor facility access areas
Decorating continues in the ground floor facility access areas

As you can see, things are progressing quickly, with many areas of the facility coming together simultaneously. This puts us in very good stead to have all assembly works completed within the next 3 to 4 weeks, leaving just the connections to bring the data centre to life ready for occupancy.

London Central Build Blog – Week 36

This week has seen modifications made to the external skin of the building, with the installation of our custom made louvred panels. These will allow our building to ‘breathe’ once the cooling system is operational, with the flow of air carefully monitored and controlled in real-time by our custom building management system.

Further cold containment system installations
Further cold containment system installations
Cold containment system in second pod beginning to enclose air filters
Cold containment system in second pod beginning to enclose air filters
First floor data hall fire exit cut into building skin
First floor data hall fire exit cut into building skin
A look at the custom metalwork being fitted to the fire escape opening
A look at the custom metalwork being fitted to the fire escape opening
A look at the newly installed first floor data hall fire escape ahead of staircase installation
A look at the newly installed first floor data hall fire escape ahead of staircase installation
First floor data hall fire escape door
First floor data hall fire escape door
First louvred panel for extraction system installed on rail-side of facility
First louvred panel for extraction system installed on rail-side of facility
Build room workstations positioned back under power and network trunking
Build room workstations positioned back under power and network trunking
Wall mounted workstation monitors positioned in build room
Wall mounted workstation monitors positioned in build room
Delivery of further cooling hardware
Delivery of further cooling hardware
Delivery of further cooling hardware
Delivery of further cooling hardware
Installation of cable backbone arms
Installation of cable containment backbone arms
Installation of cable containment backbone arms
Installation of cable containment backbone arms
Cable containment fitted to arms in back-to-back configuration
Cable containment fitted to arms in back-to-back configuration
A look at the cable containment system as it reaches down the length of the first data hall
A look at the cable containment system as it reaches down the length of the first data hall
The cable containment system reaching the lift shaft and network riser
The cable containment system reaching the lift shaft and network riser
Cable containment arms installed to end of data hall
Cable containment arms installed to end of data hall
A look at the basket bend configuration as the wall  changes depth mid-data hall
A look at the basket bend configuration as the wall changes depth mid-data hall
Completed backbone cable containment installation
Completed backbone cable containment installation

This has been a pivotal week in seeing the first data hall finally turn from a ‘semi-building site’ into a room fit for technical installations. We are very much looking forward to the weeks ahead, as the floor goes down and the racks can be positioned.